Arbitrating Take-or-Pay (ToP) Clauses in LNG Energy Contracts
Arbitrating Take-or-Pay (ToP) Clauses in LNG Contracts
Arbitrating take-or-pay (ToP) clauses in LNG contracts is a complex and high-stakes area of international energy law. These disputes often involve hundreds of millions, if not billions, of dollars.
1. The Foundation: What is a Take-or-Pay Clause?
A Take-or-Pay (ToP) clause is a fundamental provision in long-term LNG Sale and Purchase Agreements (SPAs). It is a risk-allocation mechanism designed to ensure the economic viability of the massive, capital-intensive projects required to produce and liquefy natural gas.
The Buyer's Obligation: The buyer agrees to either:
Take (accept and pay for) a minimum quantity of LNG in a given period (usually annually), or
Pay for that minimum quantity, even if they do not take delivery.
The Seller's Benefit: This guaranteed revenue stream provides the bankability for the seller to secure financing for multi-billion dollar LNG trains, pipelines, and other infrastructure.
The "Make-Up" Right: To soften the blow for the buyer, ToP clauses are almost always coupled with a make-up gas provision. If the buyer pays for gas they didn't take, they typically earn a credit (make-up gas) that they can physically take delivery of in the future, usually at a discounted price or without paying the commodity charge again, subject to certain conditions and time limits.
2. Why Do Take-or-Pay Disputes Arise?
Disputes erupt when the delicate commercial balance of the ToP clause is disrupted. Common triggers include:
Market Price Volatility: This is the most common cause. If the spot price of LNG falls significantly below the contract price (which is often indexed to oil), the buyer has a strong incentive to reduce offtake. They may prefer to buy cheaper LNG on the spot market and invoke the ToP clause, leading to a dispute over their obligations.
Demand Shocks: Events like the 2008 Financial Crisis or the COVID-19 pandemic caused a sudden, dramatic drop in energy demand. Buyers could not absorb the contracted volumes and were forced to invoke force majeure or seek contract adjustments.
Buyer's Inability to Accept Cargoes: This could be due to problems with the buyer's regasification terminal, downstream pipeline issues, or lack of storage capacity.
Seller's Failure to Deliver: If the seller fails to deliver tendered cargoes (e.g., due to production issues at the liquefaction plant), the buyer may claim this suspends their ToP payment obligation.
Disagreements on Operation: Disputes over the complex mechanics of the clause itself, such as:
The accurate calculation of the Annual Contract Quantity (ACQ).
The validity of a force majeure claim.
The application and carry-forward of make-up gas.
Nominations and scheduling procedures.
3. Key Legal and Contractual Issues in Arbitration
When a ToP dispute goes to arbitration, the tribunal's analysis will center on interpreting the specific contract language within the framework of applicable law. Key issues include:
A. Force Majeure and Hardship
Force Majeure: Buyers often argue that an event (e.g., a pandemic, a government regulation, war) constitutes a force majeure event that excuses their performance. The tribunal will scrutinize:
The exact definition of a force majeure event in the contract.
Whether the event was unforeseeable, beyond the party's control, and could not be overcome.
Causation and mitigation efforts.
Hardship / Change of Circumstances: Some civil law jurisdictions and the UNIDROIT Principles recognize the doctrine of hardship (rebus sic stantibus). A buyer may argue that a fundamental alteration of the equilibrium of the contract (like a massive price shift) entitles them to renegotiation or adaptation. This is a very high bar to meet and is often explicitly excluded in English or New York law-governed contracts, which favor pacta sunt servanda (agreements must be kept).
B. Price Review Clauses
Many modern LNG contracts include a price review clause that allows for a periodic renegotiation of the pricing formula if the market deviates fundamentally. Disputes over whether a review is triggered and what the new price should be are frequently arbitrated. A successful price review can alleviate the pressure that leads to a ToP dispute.
C. The "Reasonable Endeavards" and Mitigation
Contracts may require the buyer to use "reasonable endeavours" to avoid triggering the ToP obligation. The tribunal may examine whether the buyer made sufficient efforts to sell excess LNG or manage its demand to minimize the shortfall.
D. Interpretation of Make-Up Gas Provisions
Disputes are common over:
Expiry of Make-Up Gas: Can the seller extinguish unused make-up gas credits after a certain period?
Precedence: Does the obligation to take make-up gas take precedence over current year quantities? The specific contract language is critical.
Overtakes: Can a buyer "overtake" gas in one year to compensate for a previous shortfall?
4. The Arbitration Process for ToP Disputes
Commencement: The process begins with a Notice of Arbitration from the claimant (often the seller claiming unpaid ToP amounts, or the buyer seeking a declaration of non-liability).
Tribunal Formation: Parties select arbitrators with specific expertise in energy, long-term contracts, and international arbitration. Institutions like the HKIAC, ICC, LCIA, or SIAC are common.
Written Submissions (Pleadings): Parties exchange detailed submissions laying out their case, supported by witness statements, expert reports, and documentary evidence.
Document Production: A critical phase where parties request internal documents from each other (emails, board minutes, market analyses) relevant to the dispute.
Witness and Expert Evidence: Key fact witnesses (e.g., company negotiators) and experts (on LNG markets, valuation, industry practice, and quantum/damages) are presented and cross-examined at a hearing.
The Hearing: A multi-day (or week-long) event where legal arguments are presented, and witnesses are examined.
The Award: The tribunal issues a final, binding, and confidential award deciding on liability and damages.
5. Strategic Considerations & Recent Trends
Settlement: The vast majority of these disputes settle before a final award. The reasons are compelling: the desire to preserve a long-term commercial relationship, the extreme cost and time of arbitration, and the uncertainty of outcome.
Hybrid Claims: Parties rarely rely on a single argument. A buyer might simultaneously claim force majeure, invoke a price review, and argue that the seller failed to mitigate its own damages.
The Energy Transition: The global push towards decarbonization is creating a new wave of disputes. Buyers are increasingly arguing that government climate policies or reduced demand for fossil fuels constitute a force majeure or hardship event, frustrating the long-term purpose of the contract.
Master Limited Agreements: Many portfolios have MLAs that govern multiple SPAs. A dispute under one SPA can have implications for others under the same MLA.
Hypothetical Arbitration Scenario
Seller (an LNG producer) brings a claim against Buyer (a utility in Asia) for $500 million in unpaid ToP charges from 2020.
Seller's Case: The contract is clear. The buyer failed to take the ACQ and did not pay. The force majeure clause does not cover a general economic downturn or a drop in market prices.
Buyer's Defense:
The COVID-19 pandemic and subsequent government lockdowns were a force majeure event that made it impossible to consume the gas.
In the alternative, the pandemic created a fundamental change of circumstances (hardship), making continued performance excessively onerous.
The seller failed to cooperate in allowing the buyer to manage its make-up gas inventory, thereby exacerbating the damages.
The Tribunal's Task: To meticulously interpret the force majeure clause, analyze the causation between the pandemic and the buyer's inability to take the gas, assess the applicability of hardship under the governing law, and determine the final quantum of damages, taking into account make-up gas and any mitigation.
In summary, arbitrating ToP clauses is not a simple matter of contract enforcement. It is a nuanced process that requires arbitrators to dissect complex contractual mechanisms, apply legal doctrines to unprecedented real-world events, and ultimately decide on the allocation of massive financial risks in a volatile global market.

